In 2010, STSMCC began discussions about securing our own premises for the effective conduct of our Holy Qurbana and Catechesis classes. We looked far and beyond within Bristol and met with Bishop Declan of Clifton diocese to seek out any available churches to buy or lease. Since this option did not come to fruition, we started to look for properties suitable for a church that would meet our needs. We registered as a charity and formed a Director Board under Syro-Malabar Co-ordinator Fr Thomas Paradayil MST. 

 On 31st July 2018, we became a Mission, and the area under the Mission was extended to cover Bristol, Trowbridge, Bath, Weston-Super-Mare. 

In Nov 2018, we were successful in our bid and secured the land at Siston Common, Bristol previously known as Bridge House Farm. Prior to the bid, we conducted a feasibility study with a pre-planning application to South Gloucestershire Council.

 Soon we commenced the planning work and formed a building committee within STSMCC for planning and fundraising. Various feasibility options were explored through several meetings, and we have achieved great strides in progressing our dream project through the pandemic.  


Project Development 

02/12/2018 - Foundation stone was blessed by Major Archbishop George Alencherry.

2019 - Planning process commenced, and a Consultant Architect was appointed to develop a sustainable design and to preserve the ecosystem of the Commons land. The structure is modelled in the traditional Syro-Malabar church design, customised internally for the community. 

Oct 2019 - Planning application was submitted to South Gloucestershire Council.  

Aug 2020 - Application was refused by the Council and the community decided to appeal against the decision.  

Oct 2020 - Appeal process started with appointment of an Appeal Consultant.   

Jun 2021- We were successful in the appeal and Planning permission was granted.  The architects proceeded with discharging of planning conditions and building regulations. In the meantime, other consultants such as Quantity Surveyor, MEP, Structural Engineers, and Drainage Consultant were engaged in the process.  Discussions progressed with utility companies to upgrade the current infrastructure. 

Jul 2021- A Consultant Geologist was appointed to undertake the ground investigation. 

Jun 2022- We submitted the building regulation application, and it was approved in Aug 2022. In the meantime, pre-commencement conditions, discharging applications were submitted and were discharged one by one.  

Sept 2022- QS began the tender process to employ suitable building contractors. 

Sept 2022- Permission was obtained to demolish the existing building. 

Feb 2023- QS recommended several building contractors.

The Executive Committee and Church Building Committee meet regularly throughout the above process to be appraised of building developments and approves each stage. 

 March 2023- The various committees and the parish general body have agreed to proceed with the shortlisted tenders.

Target completion - July 2024